[Under Construction]

Some Management and Engineering Project Accomplishments of   Terry V. Molloy, PE

Pacific Gas & Electric Co.
1991-92  Setup and implemented a plan for the transition to a new cost management system for the 120 member Mechanical & Nuclear Engineering Department. This department was to first large department to be trained on the use of this system. The critical component was the need to transfer all project cost tracking, including payroll, to this system during a one week period.
1990 - 92 Managed the project to move the EPRI PIN, a data model of the life cycle of a power plant, from a paper and dBase III format to a CASE tool. This project required to coordination of work between three electric utilities and a large engineering consulting firm. 
1988-91  Guide the work of the U.C. Davis Minority Engineering Program (MEP) Industry Advisory Board to identify and serve the needs of the MEP students as opposed to focusing on recruiting these students to meet affirmative action goals. 
1984-89  Initiated changes to the PG&E College Relations Department policies for participation in the corporate Summer Technical Intern Program (STIP). The changes also impacted the way and type of students selected to participate in STIP. The results were positive for both the students and the company. We reduced recruiting cost, increased the quality of the tours, and significantly improved the full-time job acceptance rate of previous STIP participants.
1983-92  Designed and implemented a professional development program for new engineering graduates that integrated with the PG&E Mechanical & Nuclear Engineering (M&NE) department's summer intern program and recruiting strategy. While responsible for the professional development program, recruiting program, and summer intern program in M&NE, we hired over fifty percent of our new engineering graduates from our summer intern program. The coordination of the three programs resulted in a reduction of new hire costs to well below the company average, maintaining an average GPA of 3.2 for new hires, and exceeding affirmative action goals without compromising the quality standards for any of the new hires. 
1984-85  Selected by the Vice President of Engineering to lead the productivity measurement and improvement effort in the 1100 employee Engineering Department. The results of this effort were a set of performance measures to give the organization's management a better understanding of how resources were being used. 
1979-81  Functioned as the Project Engineer and Manager for a full scale Hydrogen Sulfide abatement system to be designed and installed upstream of an operating geothermal power plant unit at the Geysers. The detail design work started in September of 1980. The project was canceled in June of 1991, for a combination of political and technical reasons beyond Engineering’s control. At the time the project was canceled it was four months ahead of schedule and all major technical issues had been identified and resolved. 
1979-80  Functioned as the Project Engineer and Manager for the demonstration and test of the "Coury Process" to remove Hydrogen Sulfide from the steam upstream of the power generation facility. This process was successfully demonstrated at the Geyser's Power Plant Unit 7. A project was initiated that would allow a controlled evaluation of the process concepts for a wider range of Hydrogen Sulfide, CO2, and Ammonia concentrations in the steam. This project was to be implemented at Geysers Unit 13, the unit with the lowest H2S content. This Coury Process, in the opinion of the M&NE Department's H2S abatement consultant, had the greatest potential to reduce the cost of geothermal power generated at The Geysers. The demonstration project at unit 13 was canceled due to funding constraints and EPRI / Coury patient rights issues.  
1976 Lead the team of engineers that designed and started up the first implementation of electronic control system instrumentation at The Geysers Power Plant. This effort resulted in the acceptance of the use of electronic equipment for all future units. This resulted in significant savings through reduced design, initial equipment, installation, and O&M costs for the new units. 
1976  Lead the team of engineers that supported the installation and startup of the sludge removal systems being installed as temporary measures on The Geysers Power Plant units 3, 4, and 11. The operational date for the systems was December 31, 1976. The construction of these facilities was well behind schedule when our team arrived on site in early November. The team was able to support the construction group, resolving design questions, expediting equipment deliveries, and providing inspecting support.  The advance testing of electronic systems isolated equipment malfunctionson during the startup phase to field wiring errors. Unit 11 was operational on December 15, 1976. Units 3 & 4 became operational on December 23.  
1974  Provided the design, construction, and startup support for the first Non-condensable Gas Incinerator System at The Geysers Power Plant. This project was part of PG&E's commitment to reduce Hydrogen Sulfide emissions from the units at The Geysers and was on a critical schedule. An engineering consulting company with construction support from PG&E's General Construction (GC) Department was originally doing the project. When the responsibility for on-site was transferred our group, the project was well behind schedule. With the help of GC the project was brought on line in time to meet the regulatory commitments. 
Grove Valve & Regulator Co.
1969  Wrote a Timeshare program to support a management decision making process relative to production and shipping schedules. This program allowed the management to evaluate different scenarios related to production, cash flow, and promised shipping dates.

Return to Front Page

 

Send mail to tvmolloy@cmes.net with questions or comments about this web site.
Last modified: October 08, 2000